Construction management plan

I. Overview of the Project

Second, the site situation and the overall layout of the construction site

Third, the construction deployment

1, guiding ideology

2. Quality objective: ensure quality.

3. Time limit: according to the construction contract time limit, complete all civil engineering and installation tasks within the contract scope on time with good quality and quantity.

4. Safe and civilized construction goal: ensure safe production, successfully complete the construction task, and create a municipal civilized construction standardization site.

5. Quality management

Establish a perfect quality management system, use scientific management methods to effectively control the project, carry out process construction with high quality and high efficiency, achieve the purpose of creating a cup, meet the requirements of the owner to the greatest extent, and carry out construction according to the relevant requirements of construction drawings and construction specifications. At the same time, we must conscientiously implement management according to the provisions of our company's ISO9002 quality assurance system, and use total quality management means and three-level quality management methods. Put prevention first, change the post-event inspection of quality management into pre-event control, and change the management result into management factor, so as to nip the common quality defects in the bud and put an end to quality accidents.

Fourth, the construction preparation work

After signing the contract, our company immediately sent members of the project team to the construction site to make preparations for the entry of construction team, materials and equipment, the construction of temporary facilities and the layout of the construction site, and set out the positioning of the project to create favorable conditions for the project to start on time.

1, organize relevant engineering and technical personnel to be familiar with construction drawings and technical specifications, and make preparations for design disclosure and blue prints.the design as soon as possible.

2, combined with the actual situation of this project, according to the adopted "four new" technology or process to carry out new and special agent training.

3. Formulate a series of management systems, measures and responsibility systems for engineering technology, quality, safety, fire protection, security, statistics, finance, machinery, materials, civilized construction and logistics services.

4. Prepare the formal unit project construction organization design or scheme, project quality target guarantee plan, project quality target monitoring table, main partial construction scheme, work instruction, technical disclosure book, etc. that conform to the actual situation of this project.

5. Prepare the construction budget and demand plan for all kinds of mechanical equipment, materials and turnover materials.

6. Prepare the construction progress plan and the daily, monthly and monthly construction progress plans.

7. Conduct construction positioning and layout of elevation control points.

8. Carry out temporary construction and layout.

9. Do a good job in the layout of construction roads and water and electricity lines.

10, organize the mobilization and resettlement of construction machinery and labor.

1 1. Set up the construction signs with the image of a safe and civilized construction site, and establish perfect safety facilities.

Verb (abbreviation of verb) construction scheme

1. According to the construction principle of underground first, above ground first, structure first, decoration first, civil work first and installation later, the overall construction sequence of this project is: pile foundation-foundation-main body-roof-interior and exterior decoration-doors and windows-floor-other decoration-water and electricity installation (embedded synchronously with civil work).

2. In terms of construction arrangement and progress, according to the actual situation and the construction drawings in place, cross-flow construction shall be carried out in the construction section to improve work efficiency, speed up the construction progress, reduce the phenomenon of slowdown, and equip the corresponding construction team and labor force without affecting the construction progress.

3. After the completion of pile foundation construction, the pile foundation must be subjected to static pressure test and dynamic test. After the pile foundation is qualified, earthwork excavation and foundation construction shall be carried out immediately, so as not to affect the construction progress of the superstructure. After the foundation concrete is completed, the concrete core sample sampling test shall be conducted in time after curing, and the foundation and foundation engineering shall be accepted immediately after construction, so as to carry out the main project construction in time. After the completion of the main project construction, nondestructive testing of the strength of concrete and mortar and the detection of the thickness of steel protective layer, floor thickness and floor height should be carried out in time. After the inspection is qualified and the intermediate acceptance of the structure meets the requirements, the decoration engineering construction is in full swing. See the construction progress plan for the time limit control of each stage, and the water and electricity embedment shall be carried out simultaneously with the civil construction.

Six, the main partial project construction method

A, pile foundation construction (see pile foundation engineering construction scheme)

Second, the foundation engineering construction method:

1. Construction sequence: positioning and lofting-excavation-open trench and sump dewatering-piling-bottom cleaning and trench inspection-cushion-brick membrane-independent foundation, ground beam and floor reinforcement, formwork and concrete-basement shear wall reinforcement, formwork and concrete-basement roof reinforcement, formwork and concrete.

2. After the completion of pile foundation construction, static pressure or dynamic measurement and pile location recheck meet the requirements of design and construction specifications. After acceptance, handle the handover procedures and materials and enter the upper civil construction.

3, earthwork excavation

1) The individual foundations of this project are arranged as independent foundations, and the earthwork is excavated by large machinery, and the basement is manually trimmed. The excavated earthwork shall be piled up at a distance of 2m from the foundation trench, and some earthwork shall be transported abroad, and the retained earthwork shall be used for backfilling in the future.

2) During earthwork excavation, slope shall be put as required, and a working face with a width of 1.0m shall be reserved around the basement. Open drains are dug around the bottom of the foundation trench, collecting wells are set at four corners, and sewage pumps are provided for timely drainage. In order to prevent rainwater from flowing into the foundation trench, a waterproof berm should be built at the top of the foundation trench to prevent the foundation trench from being soaked by water.

3) After the earthwork is dug to a certain elevation, it will be driven into the basement with a 0.5m long bamboo stick, and leveled with a level as the elevation for cushion. After the foundation trench is cleaned, please ask the relevant departments to check the trench immediately and make records of the trench inspection, so as to carry out cushion construction in time and prevent the basement from being exposed for too long.

4, cushion construction:

1) When the rubble cushion is constructed, after the axis is determined, it shall be laid according to the foundation size shown in the figure, which is generally wider than the concrete cushion, and a working face of 10㎝ shall be left on one side, which shall be drained evenly according to the measured elevation, compacted, and then caulked with gravel, with the thickness of rubble cushion being 200㎝.

2) During the construction of plain concrete cushion, the elevation, thickness, flatness and strength of the concrete cushion must be strictly controlled, the elevation shall be measured with a level gauge, the tower cake and screed shall be prepared, vibrated with a flat vibrator, and then leveled and calendered by leveling personnel. The thickness of concrete cushion is 10㎝, and the design strength grade of concrete is C 15.

5, brick membrane engineering

1) After the foundation cushion is completed and watered and maintained for 24 hours, it shall be laid out and leveled on the ground. The axis, elevation and section size of brick membrane can be laid only after technical review meets the specification requirements.

2) The brick membrane of this project adopts Mu 10 fly ash brick and M 10 cement mortar, with a thickness of 120.

3) Brick membrane masonry is completed, the interior wall is brushed with 1: 2 water sand, and the layer is brushed twice, and technical review is carried out. After meeting the requirements, proceed to the next working procedure.

6, steel engineering:

The following aspects must be done well in the sub-project of steel bar: first, the quality assurance and re-inspection of steel bar raw materials should be done well; The second is to ensure the production and processing quality of steel bars; The third is to ensure the installation quality of steel binding; Four, before and after concrete pouring, to ensure that the steel skeleton is neat, to prevent man-made damage, affect the quality of reinforced concrete.

1) When the reinforcement comes into play, the appearance quality inspection must meet the requirements, and there is a quality guarantee. When the reinforcement comes into the site, it should be retested according to the specifications, varieties and quantity of the reinforcement, and it can be used in the project only if it meets the mechanical performance requirements of the corresponding reinforcement.

2) The fabrication and processing of steel bars shall be carried out at the site according to the design requirements and specifications, and the ingredient list shall be made according to the design and specifications, and the specifications shall be filled in according to the requirements of the material list, with sufficient quantity, neatly stacked according to the batches and specifications, and processed and shaped in a planned way; Steel bar turnover, production and binding installation are inseparable and complementary, and must be carried out under the guidance of turnover. Need to replace the steel bar, must be approved by the design unit, and according to the tensile bearing capacity of steel bar is equal to the design value. It is not advisable to replace it with steel bars with higher strength grades. Welded joints of steel bars shall be inspected according to batches and specifications, and can only be used after passing the inspection. Flash butt welding or double-sided lap arc welding is generally used. Conduct trial welding before rebar welding, and make records of trial welding, and conduct batch welding after meeting the requirements. Steel processing, production and inspection meet the requirements before binding and installation.

3) On-site steel binding shall be installed under the guidance of double sample, and shall be carried out in sections according to flow operation, so as to ensure that the spacing of steel bars, anchorage length, binding lap and welding joint positions are staggered as stipulated in the specification, and the quantity meets the requirements. In order to ensure the accurate position of column wall steel dowel and meet the design requirements and specifications. Especially the axis position and the thickness of protective layer, it is required to determine the axis position on the upper surface of the ground beam reinforcement, spot weld the guide stirrups of the vertical reinforcement of the column wall according to the reinforcement position required by the design, distribute and bind the column walls on the guide stirrups according to the limit requirements of the guide stirrups and their own size requirements, and bind the lower end of the steel dowel with the foundation ground beam reinforcement to ensure that the steel dowel of the column wall does not shift. The stirrup spacing of column reinforcement in independent foundation should be set according to the requirements of upper spacing, and ensure that there are not less than three stirrups.

4) 20# lead wire shall be used for steel bar binding, and lead wire shall be tied to each foundation steel bar and column steel dowel. The protective layer pads are arranged in plum blossom shape, and the spacing is not more than1m. After the steel binding is completed, carefully check the specifications, spacing, position and quantity of steel bars according to the drawings. At the same time, do a good job in water and electricity grounding and embedding, and then fill in the hidden inspection form and submit it to the relevant departments for re-inspection. After the re-inspection is qualified, the construction of each working procedure can be carried out.

7, template engineering:

The basement construction adopts plywood formwork and steel pipe support. At the same time, formwork construction must be closely coordinated with water and electricity installation and reserved embedded parts. The position of embedded parts of reserved holes must be correct. If there is any inconsistency, it should be resolved through consultation with relevant departments in time.

1) Template materials shall be prepared in advance, and the specifications and quantity shall be prepared according to the requirements of double sampling and the construction schedule. Plywood formwork is adopted in this project to improve the forming quality of concrete. According to the requirements of the construction drawings, the template design, sample processing, and strive to match the template, and the materials are reasonable. When the template is reused, the surface should be cleaned, the damaged part should be repaired and reinforced, the surface should be flat, the size should remain unchanged, and the mold release agent should be brushed before use.

2) For the installation and support of formwork, see the formwork construction scheme of the main structure.

8, concrete engineering:

1) The quality of concrete pouring is directly related to the quality of foundation engineering, so management must be strictly strengthened, and construction and quality control should be carried out in strict accordance with the company's technical standards and construction specifications. Before concrete pouring, it must be inspected and accepted by the concealed works of reinforcement, the template technology is checked accurately, and a concrete cast sheet is issued. The foundation concrete is poured one unit project at a time, and the shear wall position on the foundation plate is turned up by 250MM to be poured integrally with the foundation plate, and 3MM steel plate water stop is embedded in the construction joint.

2) Make preparations before concrete is cast. The foundation concrete strength of this project is C30 commercial concrete, and the impermeability grade is S6. Before construction, strengthen coordination and contact with commercial concrete companies, and negotiate to solve technical problems such as pouring sequence. The parking place and road of the pump truck should be cleared and leveled in advance to ensure the smooth driving and parking of the pump truck, and at the same time, the water source and power supply should be connected to meet various coordination requirements. Before concrete pouring, the garbage in the formwork should be cleaned and watered in advance.

3) Pouring basic commercial concrete, and pumping concrete with automobile pump. Considering the technical needs of automobile pumping, the concrete slump is controlled between 12 cm+2 cm, and the concrete slump is measured for each vehicle when it is cast.

4) When concrete is cast, in order to ensure the compactness of concrete vibrating, the secondary complex vibration method is adopted. When vibrating on site, according to the structural form and concrete quantity, several vibrating teams are equipped for vibrating, and the vibrator is inserted quickly and inserted slowly during vibrating. Carry out secondary vibration within the vibration limit to reduce the gap between concrete aggregate particles and close the water gap, but it is not suitable for excessive vibration. Vibrating should be carried out in one direction in turn, and it is not allowed to vibrate casually. Generally speaking, it should be done according to plum blossom insertion points, and the spacing of each insertion point should be controlled at about 30㎝. The second compound vibration will take place about 30 minutes after the first vibration. After complex vibration, smooth the concrete surface with an iron trowel, wipe it again when the concrete is initially set, and then polish it with a trowel to close the water joint. After concrete is cast, cover it with linen and water it for curing within 12 hours.

5) Generally, the curing time of concrete is not less than 14 days, and the covering time of linen is not less than 3 days. After 3 days, proceed to the next process.

6) Strengthen the on-site sampling of concrete according to regulations, with no less than one set of compressive test blocks per machine-team and per 100 cubic meter, and test the standard strength after 28 days of curing.

7) The basement exterior wall concrete is C30 commercial concrete, and the impermeability grade is S6. See the main structure construction scheme for details.

9, axis positioning, elevation transmission and settlement observation

1) Axis positioning of this project. According to the site conditions, construction drawings and related materials, before the pile foundation construction, the main axis around the building will be extended to the off-site for about 4M respectively, and the gantry pile and surrounding floors will be used as the detection points for axis upward transmission during the upward construction of this project. After the basement floor is completed, the axis can be putright to the wall and marked to realize the axis putright.

2) Elevation transfer: according to the construction drawings, a reference point shall be set at the hidden place on the site, and the elevation of the reference point of outdoor terrace or indoor terrace is generally 0.00. During earthwork excavation, use level to dig and insert 50㎝ long bamboo sticks to the excavation elevation, which provides elevation basis for the construction of stone cushion and concrete cushion. After the completion of the base, use a level to lead the reference point to the wall, and mark it.

3) Settlement observation: According to the requirements of the construction drawing, settlement observation points and special leveling points shall be set up once for each natural layer and once a month during the decoration. During installation, surveyors, instruments and installation points shall not be changed. Make original records, arrange them in time, file them, and feed them back to the design unit regularly. The position of BM reference point should be set reasonably, and attention should be paid to strengthening protection.

(3), the main engineering construction methods

The main structure of this project is cast-in-place concrete frame structure with special-shaped columns. The design strength grade of concrete below the elevation of 2.85m is C30, and the rest is C25. Cross-flow construction shall be carried out during construction. The general construction sequence is as follows: lofting, springing-binding column (shear wall) reinforcement-erection of formwork support, leveling-installation of column (shear wall) formwork, installation of beam-slab formwork-pouring column (shear wall) concrete-binding beam-slab reinforcement-pouring beam-slab concrete-concrete curing-shuttering.

1, lofting, elastic line, leveling, technical review, review and correct rear can proceed to the next working procedure, and little red dot marked axis and elevation.

2, steel engineering

Through design disclosure and blue prints.the design, combined with the provisions of construction specifications, detailed technical disclosure is made to workers from production to binding.

1) The reinforced material must comply with the design requirements, with the manufacturer's warranty, and the test center shall conduct re-inspection according to the specifications and batches after on-site sampling. The welding of steel bars shall be carried out in accordance with the regulations. Flash butt welding and electroslag pressure welding shall be adopted for the welding of steel bars, and they can be used in the project only after passing the re-inspection test and welding test. The welding test shall be carried out in batches according to one structural layer. Conduct trial welding before welding, and make records of trial welding, and conduct batch welding after meeting the requirements.

2) Before cutting steel bars, a bill of materials shall be issued and rechecked, and steel bars can be cut only after rechecking. The blanking shall be carried out in strict accordance with the bill of materials; Processed steel bars shall be listed and stacked neatly according to the order of use, and there shall be no oil stain and granular or flaky rust on the surface of steel bars.

3) For column and shear wall reinforcement, electroslag pressure welding shall be used for Ф16 or above, and binding joints shall be used for the rest. The position of steel bars at the joint shall be staggered according to the specification, and each steel bar at the joint shall be bound with 20# lead wire at least three times within the overlapping length; Use stirrups to encrypt the lap area, and the lap length must conform to the specifications. Column steel binding must be full.

4) Beam reinforcement binding shall ensure that the row spacing, spacing size and anchorage length of main reinforcement are accurate, and the positions of reinforcement and bent reinforcement meet the design requirements. In principle, beam steel bars should be welded by flash butt welding or double-sided lap welding. For the convenience of installation, excessively long steel bars can be bound and lapped, but the lap length and lap position must meet the specified requirements and be staggered according to the specifications. Beam steel binding must be full.

5) Before binding the cast-in-place slab reinforcement, draw the spacing line on the slab mold according to the designed spacing, and place the reinforcement along the spacing line to ensure accurate spacing and straight reinforcement. After the negative reinforcement is bound, it will be supported by steel bars to ensure the spacing between the negative reinforcement and the bottom of the plate. Steel bar support is φ 8 according to the design requirements, and the number is not less than one per square meter. Reinforcement support should be padded with protective pads, and plate reinforcement binding should be fully bound.

6) Steel bars shall be tied with 20# lead wire into a figure of eight, and the binding shall be firm. The protective layer of column reinforcement should be controlled by cement pad with iron wire, the height of each column should be not less than three layers, and each side around it should be not less than two layers; Cement pads shall be placed at the bottom of the beam slab, and the spacing shall not be greater than1m. The beam side is controlled by iron wire cement pad, and the spacing is not more than1m. Special attention should be paid to the location of reinforcement and its cooperation with water and electricity embedment. The cement pad should have sufficient strength and the thickness should meet the design requirements.

7) After the steel bar binding is completed, the team shall first conduct self-inspection to check the grade, diameter and quantity of steel bars.

After passing the self-inspection, the builder and quality engineer will check whether the spacing, protective layer and position meet the specified requirements. After passing the re-inspection, the person in charge of engineering and technology will conduct spot checks on the important key parts and components, fill in the reinforced concealed acceptance form, and then notify the supervision, construction unit and quality supervision station for acceptance. After the acceptance, the construction of the next working procedure can be started.

8) When binding the reinforcement of columns and shear walls, pay attention to check the number, specifications, stirrup spacing, Rachel reinforcement and the positioning of the reinforcement of columns and shear walls. Pay attention to check whether the reinforcement of corner beam joint meets the requirements of drawings and the number of stirrups between column and shear wall.

3, template engineering

Formwork engineering is an important part of concrete structure engineering. 18㎜ thick plywood is used for the formwork column and shear wall of the main structure of this project, and 18㎜ thick plywood is used for the flat formwork.

1) Template requires that the template should be designed in advance according to the drawing size, and the template raw materials should be purchased according to the construction progress, with complete specifications and quantities. In order to improve the forming quality and appearance quality of concrete, the templates of this project are basically newly purchased, and some of the original templates are also selected well, but it is forbidden to use too old templates.

2) The template should be prepared and processed in advance according to the size of the sample drawing, so as to match the template and use reasonable materials. After the template is made, it is coated with demoulding oil and neatly stacked in the designated place according to the specifications. Before the formwork is dismantled and reused, the surface should be cleaned, the damaged part should be repaired and reinforced, the surface should be flat and the size should remain the same, and it should be reused after being coated with release agent.

3) Template installation shall be controlled according to axis, elevation, section size and verticality, and the overall requirements shall be stable and firm. The support should have sufficient stability, rigidity and strength, and the structure should be simple, easy to disassemble and construct.

4) Construction sequence: column and shear wall formwork → beam slab support → column and shear wall are in place and fixed → beam bottom formwork → beam side formwork → roof formwork → stair formwork.

5) In order to prevent slurry leakage from the four corners of column concrete and shear wall, the four corners of column formwork are made into tongue-and-groove flat-fell joints, and the contact surface of formwork at the corner of column and shear wall is increased to prevent slurry leakage from concrete. Column, shear wall template should be installed at the bottom according to the axis and set the sideline, shall not be misplaced. First, the bottom is firmly supported, and the uneven base surface is leveled with 1: 2 water sand, and cleaning holes with a height of 15㎝ are left at the bottom of the formwork and the bottom of the upper beam. Column hoop support and fixture are adopted on the outside of column and shear wall formwork. The lower, middle and upper sections of the column are fastened with steel pipes, the steel pipes of the support frame are fixed with fasteners to prevent position deviation, and the middle section is fixed with clamps. The fixture spacing is generally not less than 500㎝, and the upper and lower fixtures are 20㎝ away from the upper part of column bottom. In general, the height of the column should not be less than 5 to prevent explosion. Shear walls are set with diagonal braces and reinforced with through screws to keep the formwork vertical and stable.

6) Before the formwork of column and shear wall is installed, the basement shall be cleaned, and loose stones and laitance shall be cut, cleaned and rinsed with water. Column and shear wall template should ensure the correct section size and vertical founder. For the installation of column formwork with large cross section, fixtures and supports should be added, and if necessary, the formwork should be tied with screws to prevent the formwork from exploding.

7) The basement of formwork support system adopts φ 48 standard steel pipe with a wall thickness of 3.5㎜, and fasteners are connected with the whole building. The stud spacing is 1000㎜, and the spacing between the stud on the beam side and the beam axis is ≤500. Set two vertical and horizontal tie rods (including a sweeping rod) to ensure the stability of the support. Steel pipes shall be paved with 70×50 wooden back Fang with a spacing of 400 ~ 500 ㎜, and columns shall be padded with wooden blocks. Standard beam and floor formwork support adopts bulk logs, and the diameter of the top of the logs is not less than 6CM. (See the special construction scheme for formwork and support for details)

8) Installation of beam bottom formwork shall ensure accurate positioning of column and shear wall formwork and vertical placement. In order to prevent slurry leakage and formwork expansion caused by the contact between the beam bottom formwork for commercial concrete pouring and the beam side formwork, the expanded beam bottom formwork shall be nailed with 3×4㎝ square timber according to Liang Kuan, and the beam side formwork shall be installed in 3×4㎝ square timber and nailed firmly to prevent formwork expansion and concrete. For beams and slabs with a span of more than 4m, the central bulging in the middle of 4m beams and slabs is required to be 2‰ and less than 5m. When installing, the main beam template should be installed first, and then the secondary beam template should be installed. The secondary beam formwork shall be controlled by the main beam formwork, and the bottom formwork shall be installed first, and then the side formwork shall be erected. The joints of beam bottom formwork and side formwork shall be staggered and supported according to the axis size. When the height of the side formwork is greater than or equal to 800, add φ 10 to reinforce the screw to prevent the side formwork from being deformed by compression. The formwork joints of columns and beams shall be carefully made, tightly spliced and with correct cross-sectional dimensions to prevent slurry leakage, necking and slag inclusion. Beam bottom formwork and side formwork shall be fixed firmly, and the beam bottom formwork shall be nailed with 70×50 square timber to prevent movement and blasting.

9) After the beam bottom formwork and side formwork are installed and fixed, the flat formwork can be laid after checking the axis, elevation and section size. According to the elevation, place 70×50 horizontal square timber on the support with a spacing of 300 ~ 400 ㎜, and ensure a horizontal square timber at the joint of flat formwork, and then nail the formwork flat. Nail flat template surface should be smooth, joints should be tight, avoid two pieces. In order to prevent slurry leakage, galvanized tin sheets can be nailed on the plate joints, and the flat formwork should be cleaned after installation.

10) The stair section, platform and ladder beam are cast as a whole, and construction joints are reserved for each floor section three steps above the corresponding construction floor. The stair step template adopts the fallen wood template, and the support adopts steel pipes and logs. Step 3: Leave the formwork at the construction joint on the workbench perpendicular to the bottom formwork, and leave a movable wooden model with the width of 15㎝ at the bottom formwork at the construction joint for extraction during garbage cleaning and installation after garbage cleaning.

165438+

12) The formwork can be removed only after the concrete strength reaches the formwork removal strength, and the concrete test block removed in the early stage is left at the site. Generally, after the first layer of concrete is poured, the next layer of formwork is removed, so that the formwork removal time is always more than 10 days. The non-bearing side formwork can only be removed after the concrete has a certain strength and can ensure that its surface and edges and corners are not damaged by formwork removal. For non-frame beams with a span of less than 5m, the formwork at the beam bottom can only be removed after the early strength of concrete reaches 95% of the design strength; For load-bearing frame beams with a span of more than 5m and cantilever members with a span of more than 2m, the beam bottom formwork can only be removed after the concrete strength reaches 100% of the design strength. The early formwork removal test blocks retained at the site shall be naturally cured under the same conditions as the components. After the early compressive test, the time of form removal should be determined. Only when the concrete strength reaches the design strength can the concrete structure with the support and formwork removed bear all the service loads. When the effect of construction load is more unfavorable than that of use load, temporary support must be added after accounting. In the process of dismantling the formwork, if the concrete is found to have quality problems that affect the safety of the structure, the dismantling shall be suspended until it is processed. In the process of form removal, attention should be paid to protecting concrete members to prevent concrete members from being artificially damaged due to form removal. After the formwork is removed, it should be cleaned, stacked and corrected in time, and the release agent should be painted to ensure the smooth and flat surface of the reused concrete.

4, concrete engineering

5, bricklaying project

(4) Decoration engineering construction method

1, external wall plastering (wall painting)

2, interior wall plastering (mixed mortar bottom, interior wall latex paint surface)

3, ceiling plastering:

4, stair plastering:

5, the kitchen and bathroom plastering

6. Doors and windows should be plastered.

7, skirting board

8, coating engineering

(1) exterior wall coating:

(2) interior wall and ceiling coatings

Five, roof construction method

Six, installation project construction scheme (see installation project construction organization design)

Seven, the specific construction management measures quality, time limit for a project, safety, civilized construction and other guarantee measures.

(A) the construction quality management

(II) Specific construction guarantee measures

1, construction technical guarantee measures

2, quality assurance measures and management measures

3, time limit for a project guarantee measures

(3) Safe and civilized construction