Steps of home decoration?
1. Commencement disclosure: The owner, designer and supervisor need to be present together to explain the process, acceptance criteria, additions and deletions at the construction site. About half a day.
Special attention: If necessary, dismantle and check the items that need to be kept on site, such as air conditioners, furniture, electrical appliances, etc. The owner needs to tell the foreman how to deal with it.
2. Demolition: about 3-5 days.
3. Water and electricity disclosure: Whether there is a water purifier, garbage disposal, etc. Cross together; If there is floor heating and fresh air, it is necessary to negotiate the order with the construction party. Note: Fresh air construction takes 2 days and floor heating construction takes 3 days. Cabinet measurement, heating renovation and window measurement can be done before disclosure, or before disclosure. About half a day.
4. Hydropower transformation: pay attention to the slotting of hydropower and air conditioning, and arrange construction if there is a wall-mounted toilet. During hydropower construction, bricks can be selected, windows can be changed and entrance doors can be measured. About five days.
5, water and electricity acceptance: ready to buy a switch panel, as well as angle valves and floor drains. About half a day.
6. Kitchen and bathroom wall filling and cement leveling: After the water and electricity are qualified, the groove can be filled. Remember to go downstairs to the neighbor's house to see if there is any water leakage. About 1 day.
7. Tile the balcony, brush the kitchen and bathroom for waterproofing, and do the water closing test: during this period, you can choose the floor, set the threshold stone, prepare the non-return valve of the smoke stove, and paste the jointing agent of the external corner strip of the tile. About 3-5 days.
8. Tiling kitchen and bathroom: During this period, notify the cabinet manufacturer to prepare the copy quantity, and notify the door factory to make home measurements. Install entrance door before tiling. About 3-4 days.
9. Tile or cement floor leveling: Pay attention to the maintenance of the floor. In the meantime, water heaters and check valves can be installed for gas conversion. Inform the kitchen and bathroom ceiling to measure at home. About 1-3 days.
10, plaster leveling wall and top surface: pay attention to plaster line. During this period, you can choose bathroom, electrical appliances and furniture. About 2-3 days.
1 1. Oil workers scrape putty (2-3 times): buy paint before brushing putty. About 3-5 days.
12, putty polishing: 1 day or so.
13, brush one bottom and two sides: the effect of priming paint is good, preventing the bottom layer from returning to alkali, preventing corrosion and increasing the adhesion of paint. During this period, kitchen and bathroom and balcony ceiling can be installed; Prepare switch panel lights and install them. About 2-3 days.
Even if the foundation construction is completed here, the next step is the installation of the main material. Special attention: make an appointment with the floor merchant for measurement and acceptance 10 days in advance to see if the paving conditions are met.
14, cabinet installation: 1-2 days or so.
15, door installation: 1 day or so.
16. Floor installation: about 1 day.
17, toilet installation: about half a day.
18, wall repair, land reclamation, cleaning: return excess tiles and repair main materials such as wooden doors. Find a cleaning company to do land reclamation and cleaning. About 1 day.
19. Furniture mobilization: about 2-3 days.
20. Check in after completion.
What aspects should we pay attention to in home decoration?
1, decoration materials. Decoration materials can be said to be the most important. Be sure to choose reliable people to buy good decoration materials to ensure safety and practicality.
2. Decoration layout. You can look at the online decoration cases and have a certain understanding of the overall layout of the decoration, what you plan to do in which place and what you need to purchase.
3. Install the wires first. We have to fix all the wires first, and then we can hide them when we decorate. Remember to prepare more electric plugs, which can greatly improve the convenience of life.
The bathroom floor should be non-slip. Because the bathroom is mainly used for washing, you must buy a non-slip floor, so as to avoid accidents such as falling.
5. Style of bookcase and wardrobe. We need to determine the style of bookcases and wardrobes, so as to have a good layout and decoration in the later links. You can also customize your own bookcase and wardrobe, which is very distinctive.
6. Buy furniture. After the basic decoration is perfect, you can start buying furniture, and you can choose furniture with uniform decoration style, which is very beautiful.
What are the steps for home decoration? The specific process and steps are introduced above, including measuring the room and the designer's decoration plan before construction, and then the decoration can be carried out according to the specific process. What aspects should we pay attention to in home decoration? There are many contents, such as the choice of non-slip floor and the purchase of furniture, which are also very important. All of the above answers, I hope you can refer to them.