Industrial park project establishment process and procedures

Legal analysis: approval procedures for industrial projects

Stage 1: Project filing stage (2 working days)

Examination and approval items: business license, organization code certificate, tax registration certificate and project filing.

Examination and approval departments: Industry and Commerce Bureau, Quality Supervision Bureau, State Taxation Bureau, Local Taxation Bureau and Development and Reform Bureau.

The project unit shall prepare the project introduction and project name and submit them to the "three certificates in one" comprehensive service window of the government affairs center. After the materials are complete, the industrial and commercial business license, organization code certificate and tax registration certificate shall be submitted to the window of the Development and Reform Bureau for filing.

Stage II: Construction application stage (34 working days)

Examination and approval: project site selection, land pre-examination, environmental assessment report and issuance of state-owned land certificate (16 working days).

Examination and approval departments: Land and Resources Bureau, Housing and Construction Bureau and Environmental Protection Bureau.

Examination and approval items: building civil air defense project construction permit, lightning protection device design review, seismic safety evaluation and seismic fortification requirements review, power supply application, letter of good faith responsibility, energy conservation filing, construction project planning permit, construction permit of the constructor, and fire protection design filing of construction project (18 working days).

Examination and approval departments: Civil Air Defense Office, Meteorological Bureau, Science and Technology Bureau, Power Supply Company, Human Resources and Social Security Bureau, Housing and Construction Bureau and Fire Brigade.

The project unit prepares the application materials and submits them to the comprehensive window of the industrial project of the government service center for handling.

Stage III: Completion acceptance stage (9 working days)

Examination and approval items: acceptance of lightning protection facilities, fire protection, environmental protection, completion, planning, civil air defense and urban landscaping.

Examination and approval departments: fire brigade, environmental protection bureau, housing and construction bureau, and civil air defense office.

The project unit prepares the materials, and the administrative service center organizes the acceptance department for acceptance.

Legal basis: People's Republic of China (PRC) Urban and Rural Planning Law.

Article 14 The people's government of a city shall organize the preparation of the overall urban planning.

The overall urban planning of a municipality directly under the Central Government shall be submitted to the State Council for examination and approval by the people's government of the municipality directly under the Central Government. The overall planning of the city where the people's governments of provinces and autonomous regions are located and the city determined by the State Council shall be submitted to the State Council for examination and approval after being audited by the people's governments of provinces and autonomous regions. The overall planning of other cities shall be submitted by the people's government of the city to the people's government of the province or autonomous region for examination and approval.

Fifteenth county people's government organizations to prepare the overall planning of the town where the county people's government is located, and report it to the people's government at the next higher level for approval. The overall planning of other towns shall be organized by the town people's government and submitted to the people's government at the next higher level for examination and approval.