Scaffolding must be inspected if it is out of service for more than a few months.

If it is deactivated for more than one month, acceptance inspection is required.

Scaffolding and its foundations should be inspected and accepted at the following stages:

(1) After the foundation is completed and before the scaffolding is erected;

(2) Operation Before applying load on the layer;

(3) After every 10~13m height is erected;

(4) After reaching the design height;

(5) After encountering level 6 strong winds and heavy rain; after freezing in cold areas;

(6) Disable use for more than one month.

Scaffolding usage requirements and specifications:

1. Safety

1. When erecting high-rise scaffolding, all materials used must meet quality requirements.

2. The foundation of high-rise scaffolding must be solid. It must be calculated before erection to meet the load requirements. It must be erected in accordance with construction specifications and drainage measures must be taken.

3. The technical requirements for scaffolding erection should comply with relevant specifications.

4. We must attach great importance to various structural measures: scissor braces, tie points, etc. should be set as required.

5. Horizontal sealing: Starting from the first step, every other step or two, scaffolding boards or scaffolding fences should be laid all over. The scaffolding boards should be laid along the length, and the joints should be overlapped and placed on small crossbars. , short boards are strictly prohibited. And lay a long safety bottom fence every four steps between the inner pole and the wall.