Comprehensive cleaning
Before applying waterproof paint, we need to thoroughly clean the walls and floors and blow off the dust in the corner with the air pump hose.
Embedded traverse processing
When applying waterproof coating, the treatment of inlay is the key. The internal angle of the wall-to-ground joint should be painted in a figure of eight, crossing up and down, and the intersection point should be not less than 20 cm, so as to ensure no omission.
Brush paint
Next, paint the wall along the baseline, remembering the order from top to bottom and from left to right. The ground waterproofing shall be constructed from the inside out, and special attention shall be paid to the painting of water pipe joints, and there shall be no omissions.
Closed water test
After painting is finished, don't forget to carry out the closed water test. Only after passing the inspection can the next bricklaying work be carried out.