Ceramic tile adhesive (general type)
Ceramic tile adhesive is made by mixing cement+graded sand+polymer additive through modern technology, which is mainly used to paste ceramic tiles and stones of various specifications and materials, and has various advantages such as labor saving, material saving, low cost per unit area, safety and reliability.
product specification
2KG/ bag, valve pocket
product application scope
specially used for pasting indoor tiles.
home improvement, business hotel, office building, business center, hospital and gymnasium
product construction technology
1. grass-roots treatment
grass-roots should be solid, clean, free from oil, wax, concrete curing agent and other loose objects; In the base with high water absorption or in high temperature and dry environment, the base should be wetted before construction. The smoothness of the base course should be less than .5mm per meter. If it can't meet the requirements, it should be leveled or a scraper with deep teeth should be selected.
2. Preparation of mucilage
First, add water into the mixing barrel, then slowly add the powder while stirring, stir it with an electric stirrer until it is even without caking, leave it for 3 minutes, and stir it fully again before use. The best time for use is 1 hour. See the certificate for water consumption.
3. construction technology: it is advisable to use toothed scraper for tile paving
use toothed scraper to spread the adhesive on the base to make it evenly distributed and toothed. Apply about 1 square meter each time, and then knead the tiles on the floor during the airing time. The tooth depth of the scraper should consider the flatness of the working face and the convexity and concavity of the back of the tile.
wall-baili interface agent (concrete interface treatment agent)
Concrete interface agent mainly refers to a product which is applied to the concrete surface, and can obviously improve the bonding strength between concrete and other products by increasing the roughness of the concrete surface or its own strength. It is widely used in surface treatment of various cement bases.
Wallbury interfacial agent (concrete interfacial treatment agent) is a new type of high permeability material composed of polymer emulsion and multifunctional additives. It has the characteristics of good sealing, strong permeability and high napping strength, and is suitable for interface treatment of concrete and mortar layers.
it is suitable for interface rubber coating treatment of concrete, aerated concrete and brick-concrete wall before batch putty scraping
it is suitable for base roughening on concrete layer or waterproof coating
1. Base treatment
The base should be solid, clean, free from shaking, oil pollution, wax stains, concrete curing agent and other loose objects.
2, base rubber
After diluting the interfacial agent with 5%-1% water, coat it on the base with a roller brush for 1-2 times, and then proceed to the next working procedure after being completely dried.
3. roughening of base course
The interfacial agent and cement (42.5 ordinary portland cement is recommended) are mixed in a ratio of 1:2, and brushed on the base course for 1-2 times with a hard brush, with a thickness of about 2mm. After hardening, the next process can be carried out.
Yuhong brand plugging treasure (quick setting)
Yuhong brand plugging treasure (quick setting) is a powdery waterproof plugging material made of special cement and additives through a special process. It is used for waterproof plugging on a leaking or gushing substrate and can be used for construction with water.
there are three types of water leakage in general waterproof projects, namely, point, joint and surface leakage. According to the specific situation of water leakage in the project, the quick-setting waterproof and plugging treasure can be used to treat it with different water stopping and plugging technologies.
1. Waterproof plugging of leaking holes
Waterproof treatment of the parts around leaking holes. Powder: water =1:.35 is used to mix the powder with water and apply it around the leakage hole. Generally, it is applied for 2~3 times with a trowel or scraper, and the material used for each time is about 1.2Kg/m2. Each time, after the coating hardens (without fingerprints by hand), spray it wet (but without water), and then proceed to the next construction.
remove the circular groove for plugging. Take the water leakage point as the center to carve the groove (the diameter × depth of the groove is 1mm×2mm and 2mm×3mm, and the general capillary seepage is carved into a circular hole with a diameter of 1mm), and then rinse the groove with water. Mix the powder with water and knead it into a cone with a diameter close to that of the tank. When it feels hard by hand, put it into the tank, squeeze it with a wooden stick, lightly smash it to make it compact and compact inside and around, and then stop the water instantly.
2. Waterproof plugging of water leakage cracks
Waterproof treatment of parts around water leakage cracks. Powder: water =1:.35 is used to mix the powder with water and apply it around the leaking gap. Generally, it is applied for 2~3 times with a trowel or scraper, and the material used for each time is about 1.2Kg/m2. Each time, after the coating hardens (without fingerprints by hand), spray it wet (but without water), and then proceed to the next construction. Pick up the splayed groove for plugging. Carve a splayed groove with a depth of 1mm~3mm and a width of 15mm~5mm along the crack. Put a small rope along the crack at the bottom of the tank, and the length of the rope is about 2 ~ 3 mm. After mixing the powder with water, knead it into a strip shape, put it aside for a while, and when it feels hard by hand, fill it in the groove where the rope is put, and quickly compact the edge, then pull out the rope and compact it again to make the water leak out along the rope hole. For longer cracks, they can be filled up step by step, each section is about 1mm~15mm long, and each section has a gap of 2mm wide. At the gap of 2mm, insert the nail wrapped with the mixture into the gap when the mixture is about to solidify, and quickly compact the gap around the nail with the mixture. At the same time, rotate the nail and pull it out immediately to make the water flow out along the nail hole. After the plugging material is solidified, the nail hole shall be treated according to the waterproof plugging method of the leaking hole.
3. Treatment methods for large-area water leakage
When plugging, water must be diverted to relieve pressure first. The principle of water diversion is to turn surface leakage into line leakage and point leakage, and try to reduce the leakage parts and concentrate the leakage on one or several points to reduce the seepage pressure in other parts. After that, waterproof and plugging shall be carried out according to the treatment method of point leakage or line leakage.
water Lipton high-efficiency flexible waterproof slurry
water Lipton high-efficiency flexible waterproof slurry is a two-component water-based waterproof slurry which is composed of high-quality acrylate emulsion and various additives, and inorganic powder composed of special cement and various fillers in a certain proportion. When coated on the surface of the substrate, a flexible and high-strength waterproof coating film can be formed after curing.
product specification
2Kg/ barrel
product application scope
it is suitable for waterproof and moisture-proof in bathrooms, kitchens, balconies, floors, pools and basements.
product construction technology
1. base treatment: the base surface should be smooth, solid and clean, free from sharp corners, oil stains, open water and cracks.
2. preparation of slurry: firstly, pour the liquid material into a mixing barrel, slowly add the powder while stirring, and stir with an electric stirrer until it is uniform and free from caking. When mixing, water can be added appropriately as required to adjust the viscosity when brushing. See the certificate for the preparation ratio.
3. Detail treatment: according to the design requirements, the reserved groove is embedded with sealing material; Angle of Yin and Yang, pipe root parts should be pre-processed into circular arcs or obtuse angles before construction, and grid cloth should be laid, and appropriate multi-channel brushing should be performed.
4. Large-scale construction: firstly, the base course is wetted and saturated, but there is no clear water. Waterproof coating should be painted for two or three times, and the next working procedure can be carried out only after each coating is dried, with an interval of 4-6 hours. After the coating is completely dried (estimated to be 72 hours), the closed water test can be carried out.
Haoshitu 1 high-elastic thick acrylic waterproof coating
Haoshitu 1 high-elastic thick acrylic waterproof coating is a kind of thick one-component water-borne polymer waterproof coating material which is based on high-quality modified acrylate polymer emulsion and scientifically processed by adding various additives and fillers. The coating has the characteristics of low temperature resistance and high elongation.
product specifications
2kg/ barrel, 1kg/ barrel and 5kg/ barrel
product application scope
pretreatment of corner, pipeline periphery and internal and external corners;
Waterproof and moistureproof for non-long-term immersion parts such as toilets, kitchens, floors, balconies and non-exposed roofs;
product construction technology
1. base treatment: the base surface should be smooth, solid and clean, without sharp corners, oil stains, open water and cracks.
2. Detail treatment: the reserved groove is filled with sealing material according to the design requirements; Before construction, the angle of yin and yang and the root of the pipe will be treated as circular arcs or obtuse angles in advance, covered with grid cloth and painted with multi-channel waterproof coatings.
3. Large-scale painting: to ensure that the base layer is dry, brush the waterproof coating on the treated base material, and generally brush it for two or three times according to the requirements of the use environment. After each coating is dried (at an interval of more than 24 hours), the next process can be carried out, and the next painting direction should be perpendicular to the previous direction (at 9℃) to achieve comprehensive coating.
4. closed water test: after the coating film is completely dried (about 48 hours), block the lower outlet for water storage, the water storage depth should be not less than 2mm, and the water storage time should be 24 hours, and it is qualified if the water surface does not drop significantly.
Jiashitu 1 polymer cement waterproof coating
Jiashitu 1 polymer cement waterproof coating is a two-component water-based waterproof coating which is made of high-quality modified polymer emulsion and cement as the main raw materials, adding various additives and fillers through scientific processing. It has the characteristics of high tensile strength and firm bonding with the base.
product specifications
18kg/ barrel (1kg liquid material, 8kg powder material) and 9kg/ barrel (5kg liquid material, 4kg powder material)
product application scope
it is suitable for waterproof and moisture-proof of toilets, kitchens, floors, balconies and unexposed roofs.
product construction technology
1. base treatment
the base surface should be smooth, solid, clean, free from sharp corners, oil stains, open water and cracks.
2. Preparation of slurry
Pour the liquid material into a clean mixing barrel, slowly add the powder according to the proportion while stirring, and fully stir with an electric stirrer for 3-5 minutes until a uniform mucilage without caking is generated. When stirring, water can be added appropriately as required to adjust the viscosity when brushing.
3. Detailed treatment
The sealing material shall be embedded in the reserved groove according to the design requirements; Before construction, the angle of yin and yang and the root of the pipe will be treated as circular arcs or obtuse angles in advance, covered with grid cloth and painted with multi-channel waterproof coatings.
4. Brush the large surface
To ensure that the base layer is dry, brush the waterproof coating on the treated base material, and generally brush it for two or three times according to the requirements of the use environment. After each coating is dried (at an interval of more than 24 hours), the next procedure can be carried out, and the next painting direction should be perpendicular to the previous direction (at 9℃) to achieve comprehensive coating.
5. Closed water test
After the coating film is completely dried (about 24 hours), block the drain to store water. The water storage depth should be not less than 2mm, and the water storage time should be 24 hours. It is qualified if the water surface does not drop significantly.