Special attention: If demolition is to be carried out, check the items that need to be kept at the site, such as air conditioners, water heaters, furniture and electrical appliances. The owner needs to inform the foreman how to deal with it.
2. Demolition: about 3~5 days.
3. Water and electricity disclosure: more important. If there are water purifiers, water softeners, garbage disposal, etc. And if there is floor heating and fresh air, it is necessary to negotiate the order with the construction party. Note: Fresh air construction takes 2 days and floor heating construction takes 3 days. Cabinet measurement, heating renovation, window measurement and gas meter disassembly are all carried out before or after disclosure. About half a day.
4. Hydropower transformation: Pay attention to the slotting of hydropower, punching of air conditioner and water entering electrical materials. If there is a wall-mounted toilet, pay attention to the construction. During hydropower construction, bricks can be selected, windows can be changed and entrance doors can be measured. About five days.
5. Water and electricity acceptance: At this time, we are going to buy a switch panel, which is equipped with a switch companion, an angle valve and a floor drain according to the switch panel issued by the plumber. About half a day.
6. Trench filling and cement leveling of kitchen and bathroom walls: If there is no problem in water and electricity acceptance, trench filling can be carried out. Remember to say hello to the waterproof downstairs and leave your contact information. Maybe we should go downstairs and see if there is any water leakage. About 1 day.
7. Tile the balcony, brush the kitchen and bathroom to be waterproof, and do a closed water test: during this period, you can choose the floor and confirm the floor thickness according to the ground. Set the threshold, and prepare the non-return valve of the smoke stove and the jointing agent of the external corner strip of the brick. About 3~5 days.
8. Tiling of kitchen and bathroom: During this period, inform the cabinets and manufacturers to prepare the copy quantity, and inform the door factory (wooden door and metal door) to carry out on-site measurement, and install the entrance door before tiling or floor cement leveling. About 3-4 days.
9. Tile or cement floor leveling: pay attention to water conservation of the floor. During this period, water heaters, check valves and smoke pipes were installed for gas transformation. Inform the kitchen and bathroom ceiling to measure at home. About 1~3 days.
10. Plastering and leveling of wall surface and top surface: pay attention to plastering lines. During this period, you can choose sanitary ware, electrical appliances and furniture, and make an appointment with furniture manufacturers for home measurement. About 2-3 days.
1 1. Oil workers scrape putty (2~3 times): It is best to buy paint before the first putty scraping is finished. Remember to buy rollers, some paints with rollers, and ask the foreman if they can be used. About 3~5 days.
12. putty grinding: about 1 day.
13. Brush one bottom and two sides: Don't listen to the bravado of the foreman. After polishing, you won't brush the primer, which is effective. Brush primer to prevent the bottom layer from returning to alkali, prevent corrosion, increase paint adhesion and reduce the amount of topcoat. During the period, kitchen and bathroom and balcony ceiling can be carried out; Buy a switch panel lamp to install. About 2-3 days.
The foundation construction here is ok, and the rest is just waiting for the main material to be installed. Pay special attention to the floor merchants' on-site inspection and acceptance of the floor 10 days in advance to see if they have the paving conditions.
Next, install the main material.
14. Cabinet installation: about 1~2 days.
15. Door installation: 1 day or so.
16. Floor installation: about 1 day.
17. Toilet installation: about half a day.
18. wall repair: you can return the extra tiles and repair the main materials such as wooden doors. About clearing the land and cleaning. About 1 day.
19. Put the essence into the furniture: about 2~3 days.