Six new venues will be built and 3 will be renovated in the central city; 3 will be built and 4 will be renovated in Tanghe County and Wolong District. Among them, "one stadium and two stadiums" are both newly built. The main stadium will host track and field competitions, with an estimated number of 978 participants, and is scheduled to be delivered for use by the end of 2011. The swimming pool and comprehensive training hall will host swimming and other special events and will be held this year. Completed in October.
Water sports ground (newly built): Undertakes the dragon boat competition. The number of participants is expected to be 740. At present, the project establishment report and site selection opinion letter have been approved, the terrain survey has been completed, and the preliminary design and bidding work is in progress. It will be held this year Construction started in September.
Nanyang Institute of Technology Gymnasium (newly built): responsible for men’s basketball competitions. Construction started in June this year and is scheduled to be completed by the end of 2011.
Nanyang Agricultural School Gymnasium (newly built): It is responsible for women’s basketball competitions. The geological survey and design work have been completed. Land acquisition and demolition are about to begin. Construction is planned to start before the end of this year and be completed before the end of March 2012.
Nanyang Medical College Training Hall (renovated): Undertakes the shuttlecock and shuttlecock competition, with an estimated number of 404 participants. The museum was built and in use in 2008 and will be renovated before the end of December this year.
Nanyang Normal University Gymnasium (renovated): Undertakes table tennis competitions, with an estimated number of 311 participants. The museum was built in 2006 and has been in use until now. The renovation task will be completed by the end of December this year.
Henan Institute of Technology Gymnasium (renovated): Undertakes Chinese wrestling competitions, with an estimated number of 354 participants. The museum was built in 2006 and has been in use until now. The main task of renovation will be completed by the end of December this year.
Nanyang Gymnasium: Undertakes martial arts competitions, with an estimated number of 395 participants. The museum was built in 2005 and has been in use until now. There are currently no renovation tasks.
Tanghe County Gymnasium (newly built): Undertakes the dragon and lion dance competitions, with an estimated number of 887 participants. Construction started in May this year. The main body and steel frame construction will be completed by the end of this year, and the completion acceptance will be by the end of 2011.
Qilin Villa in Wolong District (newly built): Undertakes the fishing competition, with an estimated number of 279 participants. Preparations are currently underway, and design and bidding will be completed in the second half of this year.
Nanzhao County Lotus Hot Spring Park (newly built): Undertakes the kite competition, with an estimated number of 382 participants. At present, the draft planning and design (pictures) have been submitted to the Preparatory Committee of the Agricultural Games.
Dengzhou City Hotel (renovated): Undertakes the Chinese chess competition, with an estimated number of 340 participants. It is currently under renovation and is expected to be completed by the end of this year.
Henan Oilfield Gymnasium (renovated): Undertakes the fitness Yangko competition, with an estimated number of 527 participants. The museum was built in 1995 and is in use today. Construction will begin after the renovation plan is reviewed and submitted by Sinopec.
Neixiang County Binhe Road (reconstruction): Undertakes the bicycle load-bearing event competition, with an estimated number of 295 participants. It is currently under renovation and will be completed before the end of this year.
Nanyang Military Division Militia Comprehensive Training Base (renovated): Undertakes three militia and military competitions, with an estimated number of 327 participants. It is currently being renovated and the purchase of equipment and raw materials will be completed before the end of the year.