How to work out the quota of strip foundation

Question 1: If the strip foundation contains foundation beams, how should the quota be applied? Where there is a beam-type strip foundation, if the beam height (referring to the height from the enlarged top surface of the foundation to the top surface of the beam) exceeds 1.2m, the foundation slab shall be calculated as the silo foundation, and the part above the enlarged top surface shall be calculated as the concrete wall project.

Question 2: How to calculate the quantity of raft foundation of strip foundation with independent foundation? What quota foundation is nothing more than masonry and concrete. Masonry in the quota masonry engineering, there is a masonry foundation. If the concrete is divided into beams, slabs and columns, the fixed quantities can be set separately according to the calculation of beam slab and column. Steel bars are calculated separately. The steel bars used in construction are calculated according to different models and specifications, and then fixed according to the weight t.

Question 3: How to calculate the quantity of raft foundation of strip foundation with independent foundation? What quota foundation is nothing more than masonry and concrete. Masonry in quota masonry engineering has masonry foundation. If the concrete is divided into beams, slabs and columns, the fixed quantities can also be calculated according to the beam-slab columns. Steel bars are counted separately. All steel bars used for construction are calculated according to different models and specifications, and then fixed according to the weight t.

Question 4: What is the quota of reinforced concrete strip foundation in Shandong Province? Five points. Sorry, I only stayed at the construction site for 2 months. Yes, I don't understand this. I know a little about pictures. I can help you if you have difficulties.

Question 5: What is the quota of the beam sleeve in the picture? Is it incorporated into a set of foundation or a set of foundation beam quota? Foundation beam quota

Question 6: How much quota should be set in the estimate of strip foundation? 1, the budget estimate sets the budget estimate quota.

2. After the construction is completed, check whether the budget estimate is within the budget estimate scope according to the as-built drawing. If the budget is exceeded, the settlement book shall be re-compiled according to the agreed quota, charging documents and main materials, and the excess shall be increased in consultation with the owner.

3. If there is any change in the construction, please ask the owner and designer to design the contact list in time. For the perfect part of the design department, a technical contact sheet can also be prepared and submitted to the designer and the owner for confirmation and signature.

Question 7: Trench digging with strip foundation and foundation pit digging with independent foundation? And the related calculation 1, the strip foundation only calculates the trench excavation, not the foundation pit excavation, right? The excavation of strip foundation shall be subject to the excavation quota subtitle. Ditching subtitle should be applied instead of ditching subtitle when digging foundation pit.

2. There are two calculation standards for trenching: list and quota. Do I have to count both cases? What is the final quota? The calculation rules of engineering quantity of bill pricing and quota pricing are different. Quota pricing is calculated according to the calculation rules of quota pricing quantities, so the list calculation rules are not used. The two calculation methods are different, and one quantity is calculated at the same time.

Question 8: How to calculate the earthwork of foundation beam for independent foundation? How to calculate the list and quota? The list is calculated according to the bottom area of foundation cushion x the depth of foundation pit (the bottom elevation of cushion is calculated to the delivery site elevation).

Quota is based on the outline size of foundation, adding working face at the bottom of foundation pit, adding cushion bottom at the design ground elevation, and adding slope according to different soil conditions to form the volume of a platform. (The number of places varies from place to place, and its provisions shall prevail)

Unknown. Hey, I ... I'll help you out.

If you understand, please click adopt. Thank you.

Question 9: How to set the quota of 96 for strip foundation with waterproof floor, and which quota project is suitable for waterproof floor with steel cover? The strip foundation on waterproof ground should cover the strip foundation. The floor is the foundation of the whole house, so a raft foundation should be set up.

Question 10: What is the basis? Are the materials different? How to set quotas? Strip foundation, when different, adopts conversion quota.