I. Demolition of key projects
(1) progress
Su Ding Road (Woniu Road) 1: The demolition involves 53/KLOC-0 households and 29 enterprises and institutions. At present, 508 households have signed agreements and 423 households have been demolished. Enterprises and institutions have signed agreements and 24 households have been demolished.
2. Tuohe Middle Road: 75 relocated households, including 46 in Xinbei Village, 25 in Lieshan Village and 4 in Erlangmiao Village. Since the beginning of this project, it has made rapid progress. At present, the demolition of Xinbei Village has been basically completed, and Lieshan Village has signed a contract of 2 1 household.
3. Hong Kong Street: involving 600 households, 596 households have been signed and 594 households have been demolished.
4. Hongzhuang Cultural and Creative Industry Park: involving 178 households, with 177 households signed and 175 households demolished.
(2) Main practices
1, leadership guarantee system, front command. Villages and towns involved in the demolition of key projects set up working groups to work at the demolition site every day to solve the hot and difficult problems in the demolition. At the same time, township and village cadres can unify their thinking, actively cooperate, strengthen the concept of time, seize the day, and do a good job in patient and meticulous ideological work.
2, meticulous work, solid data to the relocated households household survey, find out the basic situation of the family, the relocated households population, homestead, housing situation for registration, measurement, review, to ensure that there are no mistakes.
3. The scheme is scientific and reasonable. Before making the plan, solicit the opinions of village collectives, party member cadres and representatives of the masses, and make people-oriented within the scope of the policy to ensure the legitimate interests of the people being demolished. According to the provisions of "Huaizheng 20x25" and "Huaizheng No.20x19", combined with the actual situation, the feasible compensation standard is formulated.
4. Intensify publicity and highlight key points. At the beginning of the project, it is necessary to increase the publicity of the relocation compensation and security plan so that the relocated households can understand the policies and standards. At the same time, for the key and difficult problems encountered in the demolition work, we should take party member cadres as the breakthrough point, grasp both ends to promote the middle, and gradually advance.
5. The participating staff insisted on fair, open, just and sunny demolition operation, and achieved "unified compensation standard, unified operating procedures and unified interpretation caliber", which was recognized by the majority of relocated households and accelerated the demolition process of key projects.
Second, the problems existing in the demolition work
1, some village cadres' understanding of land acquisition and demolition work is still not in place; The level and ability to do mass work well need to be further improved.
2. The propaganda is not in place, which leads to the lack of meticulous and patient ideological work and policy propaganda in each demolition group, and sometimes unreasonable demands beyond the policy are put forward.
Healthy.
3. The forced demolition procedure is too slow.
Third, the next step
With the acceleration of the city's eastward expansion and southward migration, new regulations will be introduced soon, and the demolition task next year is particularly huge. Next year, Changshan South Road, Huaibei Normal University and other 13 projects will be integrated with Songtuan and Gurao Village, with a total area of about 165438+ 10,000 square meters, with a total of 8,885 households.
1, strengthen training and improve quality. Focus on the business training for the leaders in charge of the town office and the personnel directly involved, and seriously study the new demolition regulations that will be introduced soon.
2, a clear task, the responsibility to the people. Continue to implement the leadership guarantee system in key project areas, and further clarify the responsibilities, rights and interests of relevant departments and the town (office) where the project is located. The responsibility lies with people, and rewards and punishments are paid in time.
3. Carefully plan and formulate a scientific and reasonable relocation and resettlement plan. Next year's demolition plan, especially the overall relocation of the two houses and fields in the east and south, takes population into account as the basis for housing allocation, and each household's population is published in three lists. The population at the end of the last list is the population basis for the allocation of housing. Accessories such as houses are converted into areas by dividing the heavy price by the cost price of houses, and houses are no longer directly restored. This can not only take care of the vulnerable groups, but also effectively curb the rush to build.
extreme
In 20xx, under the correct leadership of the District Working Committee and Management Committee, our bureau adhered to the guidance of Scientific Outlook on Development, the code of conduct of "three-night requirement" put forward by the Municipal Party Committee, earnestly implemented the people-oriented concept of Yueyang governance and development, adhered to the working principle of "withdrawing one place, benefiting one place and stabilizing one party", and strictly followed the working methods of "negotiating one household, signing one household, compensating one household and resettling one household".
I. Basic information
This year, our region was successfully upgraded to an economic and technological development zone. Under the guidance of the development goal of "expanding the city eastward and developing the industry" put forward by the municipal party Committee and the municipal government, the whole region has set off a new round of large-scale urban construction upsurge. As far as our bureau is concerned, the pressure and challenges are unprecedented, the leaders have high requirements and the masses have high expectations. However, the shortage of manpower, tight time, less funds and heavy tasks are realistic problems that our bureau cannot avoid. Facing the complicated situation, all the staff of the Demolition and Resettlement Administration worked with one heart and one mind and calmly responded, and successfully completed the demolition and resettlement work in 20xx. A total of * * construction projects were started and completed, with a total investment of * * * billion yuan; A total of * * mu of land has been developed and requisitioned, and about * * million square meters of houses have been demolished, with * * households relocated. It has created four highlights of "high efficiency, quickness, harmony and safety".
Second, the specific approach:
(a), strengthen leadership, strengthen learning, solid demolition and resettlement work. Our bureau has many demolition and resettlement work sites, long lines and wide areas, involving a large number of people, great interests and complicated situations. Especially this year, the "four communities under construction" of our bureau (Miaopo, Bazimen, Liao Jia and Tea Farm) went hand in hand and started construction one after another. Without a strong leadership organization as a guarantee and rich professional knowledge as a support, this work is difficult to carry out. The party group of our bureau assessed the situation and decisively adopted the following measures: First, detailed tasks and strengthened responsibilities. According to the working idea of "one project, one leader, one model", a bureau-level leader will contact a specific project, be fully responsible for the demolition and resettlement of the project, strengthen the responsibility, and ensure that "whoever is in charge is responsible" and "whoever has problems will be investigated". The second is to pay attention to learning and practice. Since the beginning of this year, we have organized political theory study 12 times by taking party classes and watching warning films. Party member cadres wrote study notes and studied 1 10,000 words, and participated in the "Five Innovations and Quality Improvement" for * * times. At the same time, the deputy director in charge of business gave us six business knowledge classes. Through the study, the comprehensive quality of employees is obviously improved and their working ability is obviously enhanced. The third is to change the style and shape the image. Demolition and resettlement involves the direct interests of the masses, which is the most concerned, realistic and easy to cause various contradictions. The quality of demolition and resettlement work reflects the work style and level of government departments. In the demolition and resettlement work, the leading cadres of our bureau take the lead in going deep into the front line, accept supervision, carry forward democracy, and be honest and self-disciplined. All staff keep in mind the "five hearts", that is, they are enthusiastic about accepting public consultation; Carefully investigate the compensation situation; Patiently listen to the opinions of the masses; Verify the resettlement compensation standard of public interest; Care about the aftermath. Really love, benefit and empower the people.
(2), multi-channel communication, multi-directional publicity, consolidate the foundation of demolition and resettlement. The policy of demolition and resettlement is strong and the market influence is great. It is necessary to increase the publicity of relevant laws, regulations and policies, guide the masses to correctly understand and master the relevant policies of demolition and resettlement, and correctly treat the contradictions and problems in demolition and resettlement. In the work, our bureau pays attention to the publicity of relevant policies and laws and the ideological work of relocated households in various ways, forms and directions. First, hold a mobilization meeting to conduct comprehensive publicity. This year, our bureau held * * mobilization meetings, distributed * * publicity materials, hung * * banners, strengthened communication, enhanced understanding, and kept love, reason and law in the hearts of the masses forever, laying a good foundation for the smooth demolition and resettlement. Second, give full play to the radiation role of party member cadres in the village group, and make every effort to help carry out publicity. The power of example is infinite, and the leading cadres of villages and neighborhood committees are the new force in the propaganda of demolition and resettlement. It is a magic weapon for us to give full play to the radiation function of party member cadres in village groups and make full use of publicity. For example, we asked the * * * of the Bazimen neighborhood committee to be reasonable, have feelings and guidance, and carry out policy propaganda for the nearby people. These relocated households quickly eliminated their grievances and carried out the demolition smoothly. At the same time, the problems found and raised by grassroots cadres in party member are generally symptomatic and tendentious, and we always explain and explain them seriously and responsibly. Let them run smoothly. Only in this way can our demolition and resettlement work go smoothly. The third is to go to the door in a targeted manner and do a good job of publicity. Because of the wide range of demolition, many demolition policies and uneven quality of the masses, it is quite necessary to do a good job in household publicity. This year, I went to the door to publicize and persuade * * * times, and timely publicized the relevant laws and policies on demolition and resettlement. Although quite a few people are indifferent and indifferent to the demolition and resettlement staff, and some people are even afraid of words and threats, our cadres and workers have always been enthusiastic, careful, patient, caring and sincere, winning the understanding and support of the broad masses and preventing and resolving many contradictions.
3, according to the law, sunshine operation, increase the effect of demolition and resettlement. Demolition and resettlement work is related to the vital interests of everyone who has been demolished. A little carelessness will lead to contradictions and unstable factors. Only by acting in strict accordance with the law can contradictions be eliminated in the bud. First, adhere to the principles of openness, fairness and justice, promote justice through openness and ensure stability through fairness. In the process of demolition compensation and resettlement, the approval authority, approval number, use, scope, area, compensation basis and resettlement method of the expropriated land are announced. Accept the supervision of the people in the demolished area, and set up a verification team to review and investigate the objections raised by the people, correct the existing problems, ensure that the demolition and resettlement work is carried out under the principle of fairness, justice and openness, and minimize the contradictions caused by unfair demolition and resettlement. Second, insist on not being greedy, not occupying, not moving, not demanding, and demolishing and resettling in the sun. Resolutely investigate and deal with illegal acts such as unauthorized demolition, transfer of demolition business, and unqualified demolition, strengthen supervision, and resolutely put an end to the phenomenon of "turning a blind eye, seeing without checking, not checking in place, and not checking strictly" in illegal acts. At the same time, in order to strengthen cost control, implement the principle of separation of project budget and project audit, strictly implement the bidding system, and ensure that every penny is used clearly and cleanly; In order to ensure the project quality, our bureau strictly requires the construction unit to organize the construction according to the design and current specifications, and cooperate with the supervision department to supervise and manage the project quality in the form of standing by, patrolling and parallel inspection. Hold regular engineering meetings and special meetings on quality and safety in time. This year, our bureau contacted the regulatory authorities to hold 52 regulatory meetings, 24 special meetings, issued 74 regulatory notices and participated in 566 random inspections. Complete the annual demolition and resettlement project tasks with high quality, safety and efficiency. The third is to improve the operability of legal norms in the demolition and resettlement work. Because the market is changing rapidly, and the basis of compensation for demolition and resettlement is difficult to adapt to the changes in the market. In order to further standardize and legalize the compensation for demolition and resettlement in our district, it is urgent to improve the compensation methods for demolition and resettlement. This year, a group of people in our bureau made a great breakthrough in how to compensate for resettlement and demolition, which laid a good foundation for future resettlement work.
4, proper placement, sustainable development, enjoy the treatment of demolition and resettlement. This year, our bureau overcame difficulties such as poor foundation, heavy rain and tight funds, and was reasonable and sympathetic; Seek quality, quantity and stability, and do a good job in demolition and resettlement quickly, efficiently and actively. Miaopo Community, Bazimen Community, Liaojiaanzhi Community and Tea Garden Resettlement Community started construction one after another. Miaopo Huanjian Community has completed the theme project construction of 7 houses and successfully passed the acceptance, and 9 buildings are nearing completion; The demolition work and remaining problems of Bazimen residential area have all been coordinated, the design of high-rise expansion has been completed, and the construction of sewage pipeline has been completed; The demolition and construction of Liaojia Anzhi residential area was completed in an all-round way. 80% of the excavation of the first phase project was completed, and the temporary drainage pipeline (239m) of the first phase project was laid. The planned land for tea garden resettlement community is 240 mu, with a total construction area of about 270,000 square meters, and 2 100 sets of resettlement houses can be built. Now, the red line map of land survey and bt construction scheme have been determined. At present, there are * * resettlement communities for residents who have moved into relocated households, and another * * resettlement communities are under construction. For the resettlement community that has been built, our bureau will do its best: first, resettlement first, then demolition. All projects adhere to the principle of "resettlement first and then demolition" and adopt the method of "project+resettlement", and go through the formalities together with the construction projects and apply for construction together. The second is to achieve "five unifications", adhere to unified planning and design, unified construction, unified quality supervision and unified property management, and achieve high-standard planning, high-quality construction and high-level management, so that the resettlement community has perfect functions, complete facilities and is livable and suitable for business. Due to the unity, pioneering, scientific and practical planning of the resettlement community, and the unified coordination with the overall planning of the city and district, the resettlement community we built has become a beautiful landscape in Yueyang City.
Third, the existing problems:
First, the expectations of some relocated households are too high, and the compensation requirements for demolition are divorced from reality. Some require not only to solve the housing problem, but also to solve a series of social problems such as laid-off, employment, medical insurance and old-age care. Constrained the smooth development of the demolition work.
Second, due to the serious phenomenon of housing becoming non-housing, illegal construction occurs from time to time, and illegal and illegal construction exists sporadically, which restricts the smooth development of demolition work.
In the 20xx years of work, we deeply feel that the wise decision of the District Working Committee and Management Committee is the guiding light for the development of our bureau; The attention of leaders at all levels is a powerful guarantee for demolition and resettlement; The strong support of the masses is our backbone to meet difficulties; The joint efforts of all staff are the most vivid force to promote the development of demolition and resettlement work. In the new year, we will certainly continue to be pragmatic, pioneering and innovative, push forward all the work in a down-to-earth manner and achieve more brilliant results!