How to buckle the stainless steel splayed buckle?

Reinforcement binding is an important link in building construction, which is related to the safety and stability of buildings. This paper will introduce a method of eight-character buckle binding to stabilize the displacement of steel bars, so as to help everyone better master the binding skills of steel bars.

Check reinforcement

Before the beam reinforcement is put into the mould, check the reinforcement to make sure it is correct before going upstairs. At the same time, the spread of iron on the beam should also be closely connected to ensure that the steel bar is firm and unshakable.

Indicating position line

Before steel binding, a position line shall be drawn to ensure the accurate position of steel bars. At the same time, support should be set up to ensure the stability and non-displacement of steel bars.

Binding stirrup

When binding steel bars, put on stirrups first, and draw stirrup grading marks on the main reinforcement of the beam. At the same time, to install protective layer pad, to ensure that the protective layer of steel bar is correct.

Bonding plate reinforcement

When binding reinforcement, the beam should be tied first and then the plate should be tied, and the plate reinforcement should be anchored into the beam, which is more stable. At the same time, a horse stool should be added to the construction joints of the rest platform to ensure that the steel bars are stable and not displaced.

Place plastic cushion blocks

In the roofing construction, the plastic cushion blocks are cleverly placed, staggered every 800mm and horizontally aligned. At the same time, the reinforcement of the horse stool should be 900mm apart, even and tidy.

Adjusting steel bar

During roof construction, the reinforcement should be adjusted in place, and the vertical reinforcement should be positioned with a horizontal positioning frame. At the same time, it is necessary to ensure that the protective layer of steel bar is correct, not displaced and not superelevated. After passing the self-inspection, it shall be reported to the project department for acceptance, and it shall pass the acceptance requirements at one time.